Project Description

Client: Birmingham Dental Hospital Location: Birmingham Surface Area: 3km

The Challenges

The multi-million-pound Birmingham Dental Hospital had been built, and it was soon realised that expansion was necessary to cope with the increase in patient demand.  Module Co was contracted to install a modular building, which was pre-constructed off-site and delivered whole, to save time and cost.

The Requirement
KDC Plant Ltd and Lavish Construction were contracted to complete the groundworks, building foundations and civil engineering on the build.  The project consisted of a range of building construction and installation services including;
  • ground clearance,
  • building footings and foundations
  • de-commissioning of street lighting and CCTV monitoring systems
  • construction of new building for boiler rooms and electrical switch gear
  • installation of all ducting, cabling, drainage & high pressure mains water supply
  • construction of inspection chambers for all of the utilities/ services to the new ward.
  • installation of disable access ramps, road crossings, car parking barriers, block paving and tarmacking

The project was completed on time and budget.

Groundwork & Building Foundation Requirements
If you are a main Contractor who win large projects and are looking for a local supply base or a business owner with building requirements Contact Us on 0844 586 7000 to discuss your project.  For further information on our range of groundwork, construction and building services visit: www.lavishgroup.co.uk/services/